1 | Constraction of Ala-Gothuruth Bridge Balance work in Thrissur District | 12 | completed |
2 | LAC ADF 2013-14 Improvements and four laneing of punkunnam-Thoppinmoola road from km 0/000 to 0/420 (1st reach) in Thrissur LAC | 12 | completed |
3 | Budget work 2011-12 Improvements to Ayyanthole-Puzhakkal-thrissur-Model Road Phase III from west fort to ayyanthole Chungam | 12 | completed |
4 | Budget work 2015-16 Inprovements to Cheloor-Areepalam Road (BM&BC) | 9 | completed |
5 | NABARD RIDF XIX Improvements and Providing BM&BC resurfacing to Kodungallur -Athani-Airport road (part 2) km 8/000 to 18/000 (starts from boundary of thrissur district and ends at chengamanadu | 12 | completed |
6 | NABARD RIDF XIX Improvements and Providing BM&BC resurfacing to Kodungallur -Athani-Airport road (part 1) km 0/000 to 16/900 | 12 | completed |
7 | Budget work 2016-17Improvements to kuthanur-Tholanur Road km 0/000 to 6/800 and0/000 to 6/200 BM&BC | 9 | completed |
8 | Budget work 2016-17 Improvements to Anakkallu-Ammadam-Peringottukara road km 6/800 to13/812 providing BM& BC (Pallippuram to peringottukara centre) | 12 | completed |
9 | Budget work 2016-17 Improvements to Kochannur-Mannalamkunnu Road | 6 | completed |
10 | Budget Work 2016-17Construction of Ring road around kunnamkulam town in kunnamkulam LAC | 9 | completed |
11 | Budget work 2016-17Improvements and providing BM&BC to Guruvayur-Althara- Ponnani SH from km19/500 to 23/800 in Poannani LAC in Malappuram District | 6 | completed |
12 | Budget work 2016-17 Improvements to Kodakara-Vellikulangara road 2nd reach km 3/500 to 7/600 | 12 | completed |
13 | Budget work 2016-17 Improvements to mala-Annamanda (S.H) road(BM&BC) st ch 2/550 to 5/900 in Kodungallur LAC | 12 | completed |
14 | Providing BM&BC to Nellaya- Mavundrikadavu Road km 0/000 to 5/300 in Palakkad District | 6 | completed |
15 | Budget work 2016-17 Improvements to palakkad-Ponnani by widening and providing Bm&BC from km 76/456 to 80/700 in Thavanoor LAC in Malappuram
LAC |
6 | completed |
16 | Budget work2017-18 mprovements to Thrissur-Kuttipuram road (Perumbilavu- Kadavallur) km 29/300 to &31/250 to 34/315 | 9 | completed |
17 | B/W 2015-16 Providing BM & BC works to Chavakkad Blangad Chettuva Ch0/000 to 6/000 | 12 | completed |
18 | Budget work-2017-18 SS for Improvements and providing BM & BC between km 13/000 to 19/452 of Edakkazhiyur-Veliyamcode road in Ponnani LAC in Malappuram District. | 9 | completed |
19 | Special sanction 17-18 Improvements of KNR road with BM and BC from km 0/000 to 3/600 | 12 | completed |
20 | Special Sanction 17-18 – Improvements and Providing BC Renewal to Thrissur- Mannuthy Road from KM 0/000 to 5/020 in Thrissur LAC | 6 | completed |
21 | NABARD XXIV- Improvements and providing BM and BC to Thrissur – Mannamangalam road 8/200 to 15/200 (Zoological park – Hill highway connecting road) in Ollur LAC | 12 | completed |
22 | Periodic PR from km 349/000 to km 359/000 on NH 66 (Old NH 17) in the State of Kerala on EPC mode (Total length: 10.00 km) | 6 | completed |
sl no | Details of Civil Contracts including Name of project for the last 5 years | period/completion date as per |
Progres As on date of this bid |
1 | Four laning of Thrissur -Kuttippuram road from 5/750 to 19/650 viz. Puzhakkal to Choondal – Construction of KECHERY BRIDGE across Aloor river at Kechery in Thrissur district | 12 | 20% |
2 | NABARD -NABARD RIDF XXIV-2018-19 – Improvements to Kechery- Mattom Road @ km 0/000 to 5/300 | 18 | 40% |
3 | Four laning of Thrissur-Kuttipuram Road From 5/750 to 19/640 viz puzhakkal to choondal Construction of Choondal Para Bridge at Choondal in Thrissur District | 12 | 60% |
4 | KIIFB 2016-17 Improvements to Edakkunny road 0/000 to 7/850 by providing DBM and BC in Ollur constituency in Thrissur District | 18 | 8% |
5 | KIIFB Projects – 2016-17- Improvements to Akkikavu- Kadangode- Erumapetty road( km 0/00 to 9/400) in Thrissur District | 18 | 10% |